POTTER VALLEY, Mendocino County — November 21, 2026. Pacific Gas and Electric Co. expects to begin limited geotechnical test drilling at Cape Horn Dam in late November or early December, weather permitting, as engineering work continues on the proposed decommissioning of the Potter Valley Hydroelectric Project.
The expected timing was described by PG&E spokesperson Paul Moreno in a November 16 report by Mendocino Local. This is planned work; California58 has not confirmed that drilling has started or that federal regulators have approved the dam's removal.
What crews plan to investigate
According to that reporting, engineers expect to drill two initial test borings in late November or early December; five more underwater borings are planned for summer 2027. The work is intended to establish sediment and bedrock conditions and inform temporary water-control structures such as a cofferdam and bypass channel. The late-2026 work would be a preparatory engineering step, not demolition of the dam.
The report says federal dam-safety officials authorized drilling subject to technical conditions and that the utility later provided a response addressing them. A company expectation and a conditional technical authorization do not amount to approval of the overall decommissioning proposal.
Why the federal review matters
The Federal Energy Regulatory Commission (FERC) identifies the project as Docket P-77-332. PG&E filed its license-surrender and decommissioning application in July 2025. The proposal includes removing Scott Dam and most of Cape Horn Dam, while seeking authorization for an alternative New Eel-Russian Facility (NERF) to continue some water diversions. The proposal remains subject to the federal environmental-review and licensing processes.
These decisions matter to Potter Valley irrigators and residents, the Eel River fishery, the Russian River watershed, and communities whose water planning relies on the existing project. Actual changes to river flows, future diversion infrastructure and project lands require regulatory decisions and separate implementation steps; no reader should assume either that current water deliveries will stop immediately or that dam removal is already authorized.
A separate water-quality dispute
Mendocino Local also reported an unresolved disagreement between PG&E and the State Water Resources Control Board over whether a proposed alteration to minimum river releases requires a new federal Clean Water Act Section 401 water-quality certification. This is a disputed legal and regulatory question, not a settled finding that either side has broken the law. The board's position and PG&E's counterarguments should be distinguished from any later decision by FERC or a court.
How to track the next confirmed milestone
The safest source for the project's official status is FERC's project page and filings listed under P-77-332. Local water users and environmental organizations can follow official environmental notices and public participation opportunities. The prior federal scoping-comment deadline in September 2026 has passed; readers should not mistake it for an open November application window.
Sources: FERC project docket and federal overview; Mendocino Local's November 16 reporting, which directly attributes the drilling schedule to a PG&E spokesperson. Updated November 21, 2026. No test-drilling commencement or dam-removal decision has been independently verified by California58. Send records and corrections to Potter Valley News.
Support Potter Valley News
Choose how to support Potter Valley News:
Credit / Debit Card via StripeChoose your contribution amount on the secure California58 Stripe checkout. One-time support for independent local journalism.
Continue with PayPal Continue with ZelleZelle payments go to Vitaly Ataev Troshin. Please verify the recipient in your bank before sending. Availability depends on your bank.
Optional reader support. When possible, add “Potter Valley News” to the payment note. Contributions are not advertised as tax-deductible. Support does not influence editorial decisions.More from Potter Valley News
- Thanksgiving in Potter Valley: A short outing to Lake Mendocino north shore →
- Potter Valley Irrigation District: Hildebrand Leads Giuntini in Division 4 →
- New Eel–Russian Facility Could Preserve Diversions After Potter Valley Dam Removal — But It Needs Separate Approval →
- Potter Valley Roads Included in Mendocino County's 2026–27 SB 1 Maintenance Program →
- Potter Valley Irrigation Board Meets Monthly: How Farmers Can Review Water Decisions and Audits →
COMMUNITY
Comments
Join the California58 conversation. You must be signed in to comment.
Create a free California58 account or sign in with an available social provider.